Project / recent work: Pipe Line Work & Storage Tanks Source: PMS Engineering Business Profile 2026, page 7 Additional information reproduced from the profile: - CS Pipe Line Work: 2,200 mm diameter; three lines x 100 m. - Documented work: cutting, welding, jointing and protective dressing. - MS Diesel Storage Tanks: SUEZ OTV VEOLIA / Intake, Araihazar. - Additional completed record: I-16 Intake — supply, fabrication and erection. - Process stages shown for I-16 Intake: Cut / Fit / Weld / Erect / Test. Note: The source page groups pipeline, tank and intake work together; they have not been split into additional project folders.